HomeMy WebLinkAbout01010 Interlocal Agreement 54.
AMENDMENT#1
CONTRACT#01010
INTERLOCALCOOPERATIVE AGREEMENT
COORDINATED WATER SYSTEM PLAN
WHEREAS, Skagit County (hereinafter referred to as County), the City of Anacortes (hereinafter
referred to as City),and the Skagit County Public UtilityDistrict#1 (hereinafter referred to as PUD)entered
into an Interlocal Cooperative Agreement on June 10, 1991, the purpose of which was to share the costs
for a Coordinated Water System Plan (CWSP) for addressing water resource issues within Skagit County;
and
WHEREAS,the Interlocal agreement authorized funds in equal shares from each entity in the amount
of$22,133.33 each, which were to be used to hire a consultant to create the Coordinated Water System Plan
(see Contract #001700 with Economic and Engineering Services, Inc.,hereinafter referred to as Contractor);
and
WHEREAS,during the period from September, 1992, through July, 1993, the three entities requested
that the consultant perform additional tasks that are important to completion of the water resource planning
for Skagit County as follows:
1) Additional printing, drafting and assembly of copies of the CWSP
2) Address issues such as population forcasting, design standards and fire flow which relate to local '
planning under the State Growth Management Act and which arose during the course of study
3) Facilitate and assist in development of an agreement between the City and PUD for joint development
of operation of facilities
WHEREAS,the completion of these additional tasks necessitate funding above and in excess of those
funds authorized by the original Interlocal Cooperative Agreement.
NOW,THEREFORE,BE IT UNDERSTOOD that the County, the City and the PUD hereby agree to
amend Contract #01010, the Interlocal Cooperative Agreement for the Coordinated Water System Plan as
follows:
1. The total amount due to the Contractor for authorized' services performed in addition to those listed
in the original agreement with the Consultant is$33,100.00.
2. The Washington State Department of Health,hal allocated an additional $10,000 toward'a4he funding
of these additional services.
3. The costs of the remainder of the amount due ($23,100) shall be equally shared by the three entities
as follows:
City share -$7,700
PUD share -$7,700
County share -$7,700
4. The City and PUD portions in the amount of$7,700 each shall be payable to the County on or before
August 31, 1993.
5. The term of the Interlocal Cooperative Agreement shall be extended to September 30, 1993, in order
to complete the extra tasks delegated to the Consultant.
4 - -
_-'
AMENDMENT #1 TO CONTRACT #01010
INTERLOCAL COOPERATIVE AGREEMENT
PAGE #2 ..
DATE: 603. BOARD OF COUNTY COMMISSIONERS
SKAGIT COUNTY, WASHINGTON
Robert Hart,Hart, Chairman
*/avioe4—.1
Robby Ro in n, Commissioner
Aj0. .-10e-d-----
H rvey Wolden, C mmissioner _.
APPROVED AS TO FORM:
J n MJfat, Chief Civil Deputy
3
ATTEST:
n le ,'Clerlethe Board
DATE: t<i I (e (q 5 CITY OF ANACORTES
o e er, Mayor
DATE: August 3, 1993 SKAG COUNTY PUBLIC UTILITY DISTRICT #1
Le B e, Commissioner
Al LI lefield, Commiss ner
..&°) A .
(20-17r_
nes Atterbury, CommIssio tOr'711