HomeMy WebLinkAboutK2852 / 2013-133B(2) Contract Modification 2015-002B (2) ENERGY SERVICES AUTHORIZATION NO. 2015-002 B (2)
Solar Photovoltaic System
City of Anacortes
February 20, 2015
MASTER ENERGY SERVICES AGREEMENT NO. 2013-133 B (2)
The Owner and the Energy Services Company(ESCO)named below do hereby enter into this
Authorization under terms described in the following sections:
Authorization to Proceed Project Conditions
Compensation for Energy Services
I. AUTHORIZATION TO PROCEED:
Energy Services Company: Owner:
Ameresco, Inc. City of Anacortes
222 Williams Avenue South acting through the
Suite 100 Department of Enterprise Services,
Renton, WA 98057 Facilities Division,
Telephone No. (206) 522-4270 Engineering and Architectural Services
Fax No. (425) 687-3173 PO Box 41476
E-Mail Address gthorsland@ameresco.com Olympia, WA 98504-1476
Telephone No. (360) 902-7272
By 411 By
/49
Name Name Roger igfield E.
Title Ron HaXton Title Energy Program Manager
NW Rejion Director y 3/s.
State of Washington Contractor's License No. AMEREI*004PZ
State of Washington Revenue Registration No. 602 062 980
Federal Tax Identification No. 04-3512838
MWBE Certification No.
H. COMPENSATION FOR ENERGY SERVICES:
Basic Services COMPENSATION
Energy Audit and Energy Services Proposal $ 0.00
Design $ 12,442.00
Construction Management $ 7,465.00
Overhead and Profit $ 22,395.00
Measurement and Verification—Year 1 $ 527.00
Grand Total(plus WSST as applicable) $ 42,829.00
Authorization No.2015-002 B (2) Page 1 of 2
III. PROJECT CONDITIONS:
The Project Conditions contained in the Master Energy Services Agreement will be used
unless specifically changed herein.
IV. SCOPE OF WORK:
Energy efficiency measures under Contract No. 2015-002 G(2-1)will include installation
of a solar photovoltaic system, including any and all necessary ancillary equipment. The
ESCO will perform a detailed engineering design as needed to obtain Owner review and
approval of the proposed systems and to obtain bids as required. The ESCO will provide
construction management, as-built drawings, and O&M manuals. All work is per the City
of Anacortes Energy Services Proposal dated September 15, 2014.
V. SCHEDULE FOR COMPLETION
Final completion, including 1st year M&V, within 785 calendar days after Authorization to
Proceed.
2015002Bauthem
3
Authorization No. 2015-002 B (2) Page 2 of 2