Laserfiche WebLink
Contract Number 09-011-TRN-004 <br /> Modification 04 <br /> Page 2 of 3 <br /> ARTICLE III. CONTRACT TIMES AND LIQUIDATED DAMAGES <br /> Paragraph A.1.second sentence, is revised to read"Physical Completion as defined in section 108.5 of the Special Provisions shall <br /> be achieved within Seventy-Seven(77)working days of the Notice to Proceed. <br /> ARTICLE IV. CONTRACT PRICE <br /> First paragraph,first sentence is revised to read"....which is included as Exhibit B based upon the Unit Prices shown as amended <br /> through Modification 04." <br /> First paragraph,second sentence revise to read"The total contract price is Four Hundred Sixty-Seven Thousand Eight Hundred <br /> Fifteen Dollars and Twenty-Three Cents($467,815.23), including sales tax." <br /> ARTICLE VI. CONTRACT DOCUMENTS <br /> Under Paragraph B revised to read: <br /> "4. Exhibits to this Agreement include: <br /> Exhibit A: Conformed Bid Form signed by Contractor. Executed Performance and Payment Bond. Required <br /> documents submitted by the Contractor prior to the execution of Agreement as identified in the"Instruction <br /> to Bidders". <br /> Exhibit B: Exhibit B under Modification 01, superseded by Exhibit B dated May 11, 2010 under Modification 02, <br /> superseded by Exhibit B dated May 20, 2010 under Modification 03 <br /> Exhibit C: Drawing to Revise Curb Radius on I Avenue(Ref 4) <br /> Exhibit D: Drawing to Install Driveway at 1705 6th Street(Ref 5) <br /> Exhibit E: Drawing to Remove and Replace Driveways at San Juan Hotel (Ref 10) <br /> Exhibit F: Drawing to Abandon 6-Inch Waterline at K Avenue (Ref 9) <br /> Exhibit G: Drawing and Specifications to Install ADA Ramps at N Avenue and M Avenue <br /> Exhibit H: Schematic for Larger Vortech Vault <br /> Exhibit I: FHWA 1273 dated March 10, 2010 and FHWA 1273 Amendments dated May 25, 2007 and March 26, 2009 <br /> Exhibit J: Drawing and to Install storm drain at Station 5+85 and picture locating installation site <br /> Exhibit K: Sheet C20 of C22 handrail locations (Ref 7) <br /> Exhibit L: Illustrations for additional concrete and asphalt removal& restoration at L, M and N Intersections(Ref 13) <br /> Exhibit M: Field Note for storm drain connections at 1619 6th Street(Ref 17) <br /> Exhibit N: Field Note for storm drain connections at 1607 6th Street(Ref 18) <br /> Exhibit 0: Field Note to Install infiltration trenching&piping 1505& 1507 6th St.storm access behind sidewalk(Ref 19) <br /> Exhibit P: Sheet c8 of C22 new curb inlet and catch basin at Station 13+00(Ref 20) <br /> All other terms and conditions remain unchanged. <br />