Laserfiche WebLink
City of Anacortes <br /> Engineering Department <br /> P.O. Box 547 <br /> Anacortes, WA 98221 <br /> 360.293.1920 — Office 360.293.1938 - Fax <br /> Date: March 17, 2004 <br /> 28t" Street Timeline for Construction <br /> (Completed) March 3, 2004: Short plat redlines to Leonard Boudinot and Skodje for <br /> redline fixes. Will hold mylars until approval of street vacation in April. <br /> (Completed) March 3, 2004: 28th Street plans back to Engineer for final redlines <br /> March 10 (24), 2004: 28th Street project out to bid. We have selected 5 contractors. (1) <br /> Colacurcio Brothers Construction (2) G & G Excavation, Inc. (3) Construction Unlimited, <br /> Inc. (4)Lee Johnson and Sons (5) Strider Construction Company, Inc. <br /> March 15 (18), 2004: Agreement to Evans for review. Evan's to schedule a meeting to <br /> discuss if questions. Set date to sign agreement. <br /> March 18, 2004: Board of Adjustment meeting for the street vacation. (On Task 7:00) <br /> March 24 (31), 2004: Pleasant Slope Landscape and fencing plan to Planning <br /> Commission for approval. (Plans not in and reviewed in time to meet the 24th) <br /> March 24 (April 8), 2004: Bid opening for the 28th Street improvements. <br /> March 29 (April 7), 2004: Clear and Grade begins on Pleasant Slope. Construction plan <br /> approval. <br /> April 5, 2004: Council Approval of the street vacation. Ordinance will be created prior to <br /> Council meeting. This will be passed as an ordinance. (On Task 7:30) <br /> April 5 (12, 19), 2004: Council Award of 28th Street contract. <br /> April 6 (13, 20), 2004: Notice of Award to contractor. <br /> April 6, 2004: Sign short plat mylars, vacation and record at Skagit County. (On Task) <br /> April 19 (26, May 3), 2004: Anticipated Construction start date. <br />