August 18, 1998 <br /> Pre-Construction Meeting <br /> Safeway#593 <br /> Speed Garrett City of Anacortes 929-5225 <br /> Kimberly McCool COA Engineering 293-1920 <br /> Jacket Jancewicz Market Contractors 206-730-2753 <br /> Don Measamer COA Building Dept. 293-1901 <br /> Robert Joyce Safeway 206-455-8688 <br /> Jay Tomasko F.D.I. 675-0718,Mobile 425-508-4441 <br /> 1. New plans show grease interceptors&sampling manholes as required plans received <br /> 8/17—not signed yet. <br /> 2. 130 Calendar days for completion. <br /> 3. Start on 13th Street. <br /> 4. Jacek Jancewicz expects the construction fencing to be up by the end of the week. <br /> 5. Street closer on Commercial to 13th Street for sewer connection. <br /> 6. MTC to do soils and all testing. <br /> 7. Start date August 18, 1998. <br /> 8. City needs notification of any changes to plans. <br /> 9. Don noted that curb ramp at NE corner not per City standard needs 5-foot ramp landing. <br /> 10. Engineering and inspection fees not paid yet. <br />